Posted November 2011


ADMIRALTY

The proposed Admiralty Station (ADM) and Hong Kong Park Ventilation Building (HKB) under this Project are shared use facilities with South Island Line (East) (SIL(E)) that have been designed by the SIL(E) project. Construction works for ADM and HKB will be undertaken and substantially completed by SIL(E), whilst the construction of the overrun tunnel beyond ADM and minor building works will be carried out under the SCL (HUH-ADM), including:

  • Fitting out works within ADM;
  • Installation of atrium void at ADM;
  • Demolition of existing ventilation shaft near ADM atrium;
  • Spoil mucking out works at ADM and HKB; and
  • Construction of SCL portion of HKB and reinstatement works
ADM-ENG