Though the compliance to environmental legislation is a responsibility for MTR's contractors, MTR has put in place advanced monitoring and site audit arrangements to encourage our contractors to be fully compliant with environmental legislation.

Newly constructed Mong Kok Station Entrance
There are weekly environmental site audits and monitoring of noise and dust levels supplemented with occasional daily site visits. Letters and advice are issued to contractors where there is a danger of a contractor breaching any environmental legislation. Partnering with contractors is also extensively used. This compliments the training given to contractors and MTR site staff on safety and environmental issues.

In addition, MTR has maintained Milestone Payments for compliance to a Safety, Quality and Environmental site audits on the Penny's Bay Line and the Tung Chung to Ngong Ping Cable Car. Payment is not issued if the contractor fails the site audit. There were no incidents of non-payment in 2003. This practice is not standard in Hong Kong, but MTR and our contractors recognize the benefits of this system. In addition, MTR remains as the only client in Hong Kong to promote contractor achievement awards in safety, quality and environment to deserving contractors. MTR has developed a comprehensive range of tried and tested measures that are incorporated into its construction contracts to ensure that people living and working close to construction works do not experience unacceptable levels of noise. MTR monitors the noise from construction works undertaken by contractors in much the same way as it monitors its own operating railway. During 2003, all monitoring results were within legal limits.

Environment
Introduction
Breaches of Statutory Environmental Requirement
Environmental Management System
  Environmental Performance
  Legal Compliance
  Noise - Operating Railway
  Water - Operating RailwayEmissions
  Railway Construction
  Progress against 2003 Targets
Long Term Energy Supply without Renewablesoise
Management of Asset