| Objective | Targets | Status |
|---|---|---|
| Compliance and Best Practice | Prepare Corporate Social Responsibility Policy and communicate the policy to all | Achieved Partially |
Operations Division
| Objective | Targets | Status |
|---|---|---|
| Compliance and Best Practice | Zero complaint leading to abatement notice or prosecution (2003 Baseline : Zero complaint leading to abatement notice or prosecution, 100% compliance with NCO) | Achieved |
| 95% of self monitoring noise samples within NCO criteria (The scope is enlarged that train noise, construction noise permit and equipment noise are included. And the results will be reported in Balanced Score Card) | Achieved | |
| Zero complaints on exhausts from diesel locos (2003 Baseline: 0) | Achieved | |
| Zero complaints about external air quality with none leading to abatement notice/prosecution (2003 Baseline: 0 complaints and none leading to abatement notice/prosecution) | Achieved | |
| Replace all CFC refrigerant (R12) chillers with non CFC refrigerant chillers by 2015 | Achieved | |
| Meet existing MTR design criteria for Air Quality for operating railway and LAR transport interchanges | Achieved | |
| 100% compliance with WPCO on the reports submitted to EPD (2003 Baseline:100%) | Achieved | |
| Waste Minimisation | Implement land contamination reduction plan by 2003 | Achieved |
| Maintain or better than the 2003 waste paper recycling quantity (2003 Baseline:449235 Kg ) | Achieved | |
| Maintain or better than the 2003 year waste metal recycling quantity(2003 Baseline: 1204 ton) | Achieved | |
| Reduce Reduce resources use | Meeting Energy Consumption Budget 798915 and 794551MWh for 04 and 05 respectively(Budget for 2003: 821730MWh ) | Achieved |
| Maintain the Hazardous Chemical Consumption as 2003 | Achieved | |
| Maintain the Water budgeted Consumption at the top 2 departments in Operations Division | Achieved | |
| Maintain or better than the budgeted Paper Consumption on the top 5 Departments on largest paper consumption in Operations Division | Achieved | |
| Reduce the Land Contamination | 97% of first round self monitoring comply with the discharge limits stipulated in the effluent discharge licenses (Excluding pH limit, which is now under the negotiation with EPD) (2003 Baseline: 97%) | Achieved |
Project Division
| Objective | Targets | Status |
|---|---|---|
| Compliance and Best Practice | TST contractors to achieve 100% compliance with noise, air and water regulations (Baseline: Non-compliances for similar TKE contract ( 6 Noise, 1 Air, 2 Water) | Achieved |
| PBL contractors to achieve 100% compliance with noise, air and water regulations (Baseline: Non-compliances for similar TKE contract ( 3 Noise, 4 Air, 5 Water) | Achieved | |
| Full Compliance with all Environmental Permit Conditionsfor Tung Chung Cable Car Project. | Achieved | |
| Cable Car contractors to achieve 100% compliance with noise, air and water regulations | Achieved | |
| Maintain the ecological value of North Lantau area and compensate the loss of vegetation due to Cable Car project.(a) 60% or higher survival rate of the transplanted flora species for Cable Car project; | Achieved | |
| Maintain the ecological value of North Lantau area and compensate the loss of vegetation due to Cable Car project.Plant not less than 600 trees near the new Ngong Ping Stream for Cable Car project | Achieved | |
| Achieve 98% attendance at safety and environmental induction for staff working in the country park | Achieved | |
| Waste Minimisation | Reduce by 2% or more the amount of Cable Car construction and demolition materials disposed at public fill by maximizing the opportunity for offsite reuse of the surplus materials | Achieved |
Property Division (Property Development)
| Objective | Targets | Status |
|---|---|---|
| Reduce resources use | Adopt energy saving fittings and electronic ballasts in new buildings |
Achieved |
Adopt a variable speed pumping system or direct feed system for potable water supply system for new shopping centres |
Achieved | |
Within MTR・s sphere of influence, encourage contractors to use off site pre-fabricated modular construction. |
Achieved | |
Within MTR・s sphere of influence, encourage contractors to use dry wall construction. |
Achieved | |
Within MTR・s sphere of influence, encourage adoption of metal formwork instead of timber formwork for building construction in new development sites |
Achieved | |
Within MTR・s sphere of influence, encourage the use of tropical hardwood from managed sources only |
Achieved | |
| Education & Dissemination | Encourage staff to attend training programmes on environmental matters and concerns. |
Achieved Partially |
Keep staff abreast of latest technology which are environmental friendly. |
Achieved Partially | |
As appropriate, conduct further study trips to acquire information on the latest building design and construction technology |
Achieved | |
Within MTR's sphere of influence, encourage developers to adopt Environment Management Systems. Comply/ implement the requirements of the Corporate EMS as applicable to the Property. |
Achieved | |
| Education & Dissemination | Within MTR's sphere of influence, encourage developers to incorporate Green and Innovative Buildings Practice Notes into the design of new developments |
Achieved |
| Compliance and Best Practice | As applicable, undertake EIAs for new development projects and fully comply with the requirements of the issued Environmental Permits |
Achieved |
Comply with air, noise and water pollution control ordinances for new property developments |
Achieved |
Property Division (Property Management) - Hong Kong Properties
| Objective | Targets | Status |
|---|---|---|
Resources Use |
Replacement of incandescent lamp bulbs with energy efficient compact fluorescent lamps in all common areas of MTRC managed properties. |
Achieved |
Waste Minimisation |
Full implementation of noise pollution control policy and management system. |
Achieved |
| Use zero ozone depletion potential refrigerant for chiller plant repairing works. | Achieved | |
| Re-use the disposed construction materials (e.g. Hoarding board, shopfront glass panel, glass door etc.) for renovation work and spare part for future maintenance use. | Achieved | |
| Replacement of G.I. fresh water downfeed pipes and C.I. soil and waste drainage pipes with copper pipes and UPVC pipes respectively. | Achieved | |
| Education & Dissemination | Waste recovery (plastic bottles, aluminium cans and paper) in managed properties. | Achieved |
|
Continual promotion of environmental protection by estate managers. |
Achieved |
Compliance and Best Practice |
100% compliance with air pollution, noise, water pollution control ordinances for operation, maintenance and renovation works. |
Achieved |
| Monitoring of tenant fit-out works and operation for compliance with statutory requirements. | Achieved | |
| Conduct positive measure to prevent existence of legionnaires disease in HVAC system at MTRC managed properties. | Achieved |
Property Division (Management) - International Finance Centre 2
| Objective | Targets | Status |
|---|---|---|
| Reduce resources use | Reduce Diesel/petrol consumption by goods van and a petrol car. |
Achieved |
Reduction of energy consumption resetting chilled water temperature at Winter and Summer. |
Achieved | |
Using electronic ballasts for fluorescent lights at carparks (by phase). |
Achieved | |
Switch Off unnecessary lighting in common areas of tower and carpark. |
Achieved | |
Switch Off escalators at none peak hours at carpark |
Achieved | |
Energy management of building services systems by means of building management system |
Achieved | |
Trail run of employing tube cleaning system for the heat exchangers of chillers (by phase) |
Achieved Partially | |
| Waste Minimisation | Use of zero ozone depletion potential refrigerant for chiller plant repairing works. |
Achieved |
Re-use the disposed construction materials (e.g. protection materials, hoarding board, raise floor, suspended ceiling panel etc.) for renovation work and keeping as spare part for future maintenance. |
Achieved | |
| Waste Minimisation | Recycling waste (plastic bottles, aluminum cans, paper, cartridges of printers etc.). |
Achieved |
| Education & Dissemination | Continuously promote environmental best practice by internal audit. |
Achieved |
| Compliance and Best Practice | Fully comply with current legislations such as air pollution, noise control, water pollution control ordinances for operation, maintenance and renovation works. |
Achieved |
Monitoring tenant fit-out works and operation for compliance with statutory requirements. |
Achieved |
Property Division (Management) - Kowloon Properties
| Objective | Targets | Status |
|---|---|---|
Waste Minimisation |
Use zero ozone depletion potential refrigerant for chiller plant repairing works. |
Achieved |
| Re-use the disposed construction materials (eg. Hoarding board, shopfront glass panel, glass door etc.) for renovation work and spare part for future maintenance use. | Achieved | |
| Continue the replacement of C.I. S&W drainage pipe with more durable material e.g. UPVC pipes at Luk Yeung Sun Chuen and Telford Gardens. | Achieved | |
Education & Dissemination |
Waste recovery (plastic bottles, aluminium cans and paper) in residential estates. |
Achieved |
| Compliance and Best Practice | 100% compliance with air pollution, noise, water pollution control ordinances for operation, maintenance and renovation works. | Achieved |
| Full implementation of noise pollution control policy and management system. | Achieved | |
| Carrying out environmental assessment and justification before procurement of materials/equipment and implementation of works. | Achieved | |
| Monitoring of tenant fit-out works and operation for compliance with statutory requirements. | Achieved | |
| Regular cleaning of fresh water tank i.e. 4 times per year. | Achieved | |
| Conducting positive measure to prevent existence of legionnaires disease at Telford Plaza and Luk Yeung Galleria. | Achieved |
Property Division (Management) - LAR Properties
| Objective | Targets | Status |
|---|---|---|
Reduce resources use |
Replacement of Tungsten filament light bulbs by compact fluorescent tubes for energy saving and reduction in heat generation in all newly handed over LAR properties which include Seaview Crescent (T5), Coastal Skyline (T2, T5, Clubhouse, Carpark), Harbourside. |
Achieved |
Reduction of unnecessary lighting for energy saving in all newly handed over LAR properties. |
Achieved | |
To install :Voltage Reduction System; on lighting for energy saving in Sorrento, the Waterfront, Seaview Crescent. |
Achieved | |
Reduction of energy consumption by setting higher room temperatures for air-conditioned spaces in Club House. |
Achieved | |
Reduction of energy consumption by setting a higher chilled water supply temperature during off-peak seasons. |
Achieved | |
Waste Minimisation |
Re-use of disposed construction materials (e.g. Hoarding board, shopfront glass panel, glass door etc.) for renovation works and spare parts for future maintenance use |
Achieved |
Waste Minimisation |
Waste recovery (plastic bottles, aluminium cans and paper) in residential estates. |
Achieved |
Education & Dissemination |
Continue to encourage contractors to set up procedures to manage environmental complaints form both internal and external parties. |
Achieved |
|
Continuously promote environmental best practice by estate managers. |
Achieved |
Compliance and Best Practice |
100% compliance with air, noise and water pollution control ordinances for operation, maintenance and renovation works |
Achieved |
Monitoring of tenant fit-out works and operation for compliance with statutory requirements. |
Achieved | |
Full implementation of noise pollution control policy and management system. |
Achieved | |
OZONE Depleting Substances |
Use of zero ozone depletion potential and high efficiency refrigerants for chillier plant repair or replacement works. |
Achieved |
Finance Division
| Objective | Targets | Status |
|---|---|---|
| Reduce Air Polution | Ensure 100% use of pollution-free mechanical handling equipment | Achieved |
| Ensure 100% fitting of particulate removal device to pre-euro diesel road vehicles. | Achieved | |
| Ensure 100% use of lead free gasoline road vehicles. | Achieved | |
| Compliance and Best Practice | Ensure 100% compliance with the EPD regulations on Chemical Waste disposal and handling. | Achieved |
| Waste Minimisation | Continue to exercise the recycling program of PC equipment and to re-use PC equipment by 50% | Achieved |
| Green Procurement | Continue to purchase OA equipment and stock items using green procurement guidelines | Achieved |
| Reduce resources Use | Within the boundaries of the relevant legislation governing Company Reporting, reduce the printing and distribution of Company Reports and circulars. | Achieved |
| Sustainability Accounting | Continue the sustainability accounting project for inclusion in Corporate Sustainability Report | Achieved Partially |
Legal and Procurement Division
| Objective | Targets | Status |
|---|---|---|
Resources Use |
Green Procurement |
Achieved |
|
Paper Reduction |
Achieved |
Waste Minimisation |
Disposal Procedures |
Achieved |
|
Waste recovery (plastic bottles, aluminium cans and paper) in residential estates. |
Achieved |
Education & Dissemination |
Internal Education & Training |
Achieved |
|
External Education & Training |
Achieved |
Compliance and Best Practice |
Continue to facilitate the award of EIA contracts for all Divisions. |
Achieved |
Implement the Divisional Environmental Management System established and support the Corporate EMS. |
Achieved | |
Expand third-party (supplier/contractor) audits to make suppliers aware of MTR policy on environmental priorities. |
Achieved |
Human Resource and Administration Division
| Objective | Targets | Status |
|---|---|---|
Education & Dissemination |
Organize and support training activities for non-MTR staff such as contractors to promote environmental-friendly operating & maintenance functions. |
Achieved |
|
Disseminate information on new environmental policies through training activities or communication sessions |
Achieved |
Compliance and Best Practice |
Ensure all goods/equipment/waste received/scraped/disposed of by OTD are coping with Corporate Environmental Policy and OTDIMS requirements |
Achieved |
|
Implement the Divisional Environmental Management System established and support the Corporate EMS. |
Achieved |
Sustainability |
Maintain open staff communication and consultation particularly if the Government decides to go ahead with the merger. |
Achieved |
| Implement the Action Plan formulated for addressing the Corporate issues identified from the 2003 Staff Attitude Survey results. | Achieved | |
| Should the Government decide to go ahead with the merger, conduct detailed studies on various aspects related to HR and plan for merger integration. | Achieved |